When planning a whole house customization project, one of the most common questions homeowners and developers ask is: How long does it take from start to finish?
The realistic answer is 2 to 6 months, depending on the size of the property, design complexity, materials selected, and how well the project is coordinated.
Below is a clear, step-by-step timeline that you can directly use to plan your whole house customization project.

Typical Whole House Customization Timeline (Quick Overview)
- Standard apartment: 2–3 months
- High-end apartment: 3–4 months
- Villa or luxury residence: 4–6 months
- Overseas or large-scale projects: 4–7 months
Phase 1: Design & Planning (2–4 Weeks)
This phase defines the success of the entire project.
What happens during this stage:
- On-site measurement or layout confirmation
- Space planning for kitchen, wardrobes, storage, and living areas
- Style selection (modern, minimalist, luxury, etc.)
- Material and finish selection
- Budget alignment and design revisions
A clear and finalized design helps avoid delays later. Projects with fast decision-making can complete this stage in about 2 weeks, while multiple revisions may extend it to 4 weeks or more.
Phase 2: Manufacturing & Production (4–8 Weeks)

Once the design is approved, production begins.
Average production time:
- Standard custom furniture: 4–6 weeks
- Complex designs or premium finishes: 6–8 weeks
- Stainless steel cabinets or special materials: 5–7 weeks
Factors that influence production time:
- Material availability
- Custom finishes and surface treatments
- Quantity of furniture
- Quality control standards
Factories with strict quality control may take slightly longer, but this usually results in fewer installation issues and better long-term durability.
Phase 3: Delivery & Logistics (1–3 Weeks)

Delivery time depends largely on the project location.
- Local or domestic delivery: 3–7 days
- Regional or cross-border shipping: 1–2 weeks
- Overseas export projects: 2–4 weeks (including packing and customs clearance)
Proper export packaging and clear logistics planning help reduce on-site delays.
Phase 4: Installation & On-Site Fit-Out (2–4 Weeks)

Installation speed depends on project size and site readiness.
Average installation duration:
- Apartment projects: 1–2 weeks
- Villas or large residences: 2–4 weeks
Installation includes:
- Kitchen cabinet installation
- Wardrobes and storage systems
- Hardware and accessories
- Final adjustments and inspection
If walls, flooring, plumbing, and electrical work are completed in advance, installation can be significantly faster.
What Can Cause Delays?
Even well-planned projects may face delays due to:
- Design changes after production has started
- Material shortages or long lead-time finishes
- Construction site not ready for installation
- Poor coordination between contractors and suppliers
How to Reduce the Overall Timeline
Experienced clients usually follow these best practices:
- Finalize all designs before production
- Avoid changes once manufacturing begins
- Confirm materials early, especially imported finishes
- Ensure the site is fully prepared before installation
- Work with a one-stop customization supplier
These steps can reduce delays and improve overall efficiency.
Final Answer: How Long Does Whole House Customization Really Take?
- Minimum: About 2 months (simple apartment, efficient process)
- Average: 3–4 months for most residential projects
- High-end or villa projects: 4–6 months
Whole house customization is a detailed process that balances design, craftsmanship, and coordination. A realistic timeline ensures better quality, smoother installation, and a result that meets long-term expectations.